What's happening?
Wellington City Council has contracted Fulton Hogan to complete maintenance on the footpath, kerb and channel. This work will be completed as highlighted on the map.
If you have questions, please use the contact details below or ask to talk with the supervisor on site.
College Street, between Tory Street and Cambridge Terrace
Sunday 9 February 2025
Thursday 20 February 2025
Between 7pm and 5am
Delays?
Some work is weather dependant and in the event of unsuitable weather or other unforeseen circumstances the contractor might encounter the work may be delayed, if you require an update, please use contact details below.
Please ensure your vehicle is parked clear of the worksite.
To do this work we need the work area to be clear of vehicles and other obstructions so parking will be affected Please see the map for the work and no parking areas. If your vehicle is parked in the highlighted area, we may have to tow it to a suitable park nearby. Should your vehicle be moved. please check nearby streets first before ringing the contractor listed below.
Will these roadworks affect access to my property?
At times during phases of work you may experience some delays with access, If you have to leave your property and access is obstructed please speak to our staff onsite. In the case of an emergency, essential services will be given priority. If you are expecting a delivery or have a tradesperson needing access, please contact us and we will navigate them through the work site.
Rubbish collection and recycling will continue as usual.
Will there be impact to bus services?
Bus services will not be affected and run as usual.
What traffic management will be used during this work?
A semi road closure and a 2-way stop go will be in place as Traffic Management. This will be accompanied by a reduced speed limit.
Pedestrians will still be able to use the route but please follow the directions of our staff when passing through the work site. There is no cycle lane through the work area. Cyclists will be expected to follow the same route as normal traffic or dismount and use the footpath. Parking restriction cones will be installed one day prior to works commencing.
Take care
To avoid trekking dirt, bitumen, or other materials inside, please try not to walk on open or recently sealed surfaces. If you must, check or remove your shoes before going indoors or getting into vehicles. For advice on removing trekked material, call the contact listed below.
Will we be back?
Yes, this work is in preparation for road resurfacing within the next 12 months.
Thank you
Roadworks can be disruptive for residents - please bear with us. We will be doing all we can to minimise the impact on your household. We appreciate your cooperation and patience which will help us get the job done as quickly as possible.